The City renewed five tracks covered sports halls of the parishes of Sangonera la Verde, San José de la Vega, Santo Angelo, Beniaján and Bacons Bridge.
The aim is to improve sports facilities for citizens to play sport in quality sports facilities.
Likewise, construct a building with dressing rooms attached to the sports center of Llano de Brujas.
The planned investment in the improvement of sports facilities is 505,000 euros, while in the changing rooms provided 483,025 euros.
The Governing Board has approved these projects for submission to the State Fund for Employment and Local Sustainability.
The works to be performed:
-Sangonera la Verde.
This infrastructure is in the sports of the hamlet.
The works involve the repair and rehabilitation of pavement and installation of hanging baskets in basketball.
The deadline for entries is two months and work 8 people.
The investment is 100,705 euros.
-San José de la Vega.
The track is in the sports hall complex in the hamlet.
It will repair and rehabilitate the pavement and install baskets for basketball.
Lead time is two months and will employ 8 people.
The budget is 101,178 euros.
-Holy Angel.
This infrastructure is in the sports of the hamlet.
The works involve the repair and rehabilitation of pavement and installation of hanging baskets in basketball.
The deadline for entries is two months and work 8 people.
The investment is 100,013 euros.
-Beniaján.
The clue is in the sports hall.
It is planned to repair the pavement and installing basketball hoops.
The deadline for entries is two months and work 8 people.
The investment is 99,809 euros.
"Bacons Bridge.
This track is in the sports and the goal is to repair the pavement.
The deadline for entries is two months and work 8 people.
The investment is 103,673 euros.
"Llano de Brujas.
Is to construct a building of changing facilities at the existing sports center in Llano de Brujas.
It will be a building of about 350 square meters for 4 dressing rooms for teams (two male and two female), two referees changing rooms and storage.
You will also have solar panels for hot water.
The deadline for execution of work is 6 months and will employ 20 people.
The planned investment is 483,025 euros.
Source: Ayuntamiento de Murcia