Improvements in twelve schools in the municipality of Murcia (13/01/2010)

The works consist of repairs covered under pavement, installation of taps with aerators to save water and repair of blinds, including

The City made improvements in twelve schools in the municipality in order that students can enjoy better facilities.

It is mainly pavement repairs, covers, blinds and installations of security features and systems to save water.

The Governing Board approved the project explanatory memoranda for submission to the State Fund for Employment and Local Sustainability.

The planned investment is 1,268,000 euros and will employ 154 people.

The works to be undertaken are:

CEIP-Infanta Elena, Beniaján.

Settlement of pavements, patios firm and drains.

Adequacy of the sliding door, fitness equipment store, installation of guards on the gates of Child and installation of faucets with water saving aerator.

The planned investment is 68,900 euros and will employ 12 people.

Lead time is 60 calendar days.

Sacred Heart-CEIP, Zeneta.

The works to be undertaken are replacement of roof, interior paint, blinds repair, carpentry repairs and various plumbing repairs and locksmith.

The investment is € 150,000 and employed 17 people.

Lead time is 60 calendar days.

Pedro Martínez-Handle CEIP, Boatmen.

The work consists in the adequacy of housing in the main building and the installation of guards on the doors of Children.

The budget is 120,000 euros and will employ 11 people.

Lead time is 60 calendar days.

CEIP-Infante Don Juan Manuel, Murcia.

It will rehabilitate the deck floor and will suit strong, and carried out the installation of guards on the gates of Child and installation of faucets with water saving aerator.

The estimated investment is of 177,000 euros and will employ 15 people.

Lead time is 60 calendar days.

"CEIP Los Alamos, Murcia.

This center is expected to fit the fencing and walls, and paint, fitness floor and plumbing repairs.

The budget is $ 84,000 and will employ 13 people.

The implementation period is 60 days.

"CEIP Santa Maria de Gracia, Murcia.

The work consists of installation of ramps to the kindergarten classrooms, fitness flooring, installation of guards on the doors of Children, installing faucets with water saving aerator, locksmithing and painting works in the building interior and Child some areas of the main building.

The planned investment is 60,000 euros and will employ 11 people.

Lead time is 60 calendar days.

"CEIP Monteazahar, Beniaján.

The works to be made will cover fitness, terrace and fencing, interior painting with previous repairs, improved carpentry, locksmith and plumbing and installation of child protection at the gates of Education.

The budget is 150,000 euros and the works will employ 10 people.

Lead time is 60 calendar days.

"CEIP Contraparada, Javalí New.

This center will adjust the fence walls, repairs will be made firm and patio floors, painting the old building comprehensive, including the cover and make repairs and paint the area of Education.

The investment will be € 170,000 and the number of employees will be 12.

Lead time is 60 calendar days.

"CEIP Angel Zapata, Torreagüera.

The papers will be: repairs covered with matching downpipes, painting facades and metallic elements with previous repairs, improved toilets, partial interior painting, fences and partial adaptation of doors, and flooring firm.

The project budget is € 100,000 and has involved 12 people.

Lead time is 60 calendar days.

"CEIP San José de Calasanz, Stables.

This project will adapt the deck, patio and condition the child protectors installed on the doors.

The amount of the works is € 80,000 and employ 10.

Lead time is 60 calendar days.

"CEIP Ciudad de Murcia, Murcia.

The work to be performed are repairing damaged walls, facades cleaning after coating paint, replacement of shutters, adjustable aluminum sliding windows consisting of replacement of bearings and partial adaptation of the courtyard.

The budget for these works is € 70,000 and they will hire 11 people.

Lead time is 60 calendar days.

Master-CEIP José Castaño, Murcia.

The works to be carried out in this center are: paint fence with internal partitions, floor and firm adaptation in patios and sidewalk perimeter locks in specific areas, installation of taps with aerator built on wooden joinery and adequacy of floors indoors.

The cost of the work will be of 38,100 euros and employ 121 people.

Lead time is 60 calendar days.

Source: Ayuntamiento de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information