The Governing Board approved a construction project to divert a gas pipeline in the area of Juan Carlos I and the cemetery of Espinardo to no problems with the work being undertaken for the construction of the North Coast .
The gas pipeline has a length of 300 meters and will be diverted not to interfere with the work of the North Coast and other works being carried out in the area.
To perform this work will not be necessary to cut traffic on any roads around it.
Lead time is 2 months and the investment made by the City is over 230,000 euros.
The construction project was written by Urbamusa.
Moreover, in this same area are doing works for the construction of a new roundabout at Juan Carlos I, in the old national road N-301 (road to Madrid), at the height of the electrical substation and the entrance to the cemetery Espinardo .
The roundabout will eliminate the current link is formed by an underpass and small islands, making possible all movement.
Also build a new highway connecting Juan Carlos I to the southern entrance to the Campus de Espinardo, improving north and south to the University of Murcia and facilitating the flow of traffic.
Source: Ayuntamiento de Murcia