This morning and have begun to see the early work of the renovation of sidewalks that will be undertaken in the coming weeks in Gran Vía sculptor Francisco Salzillo.
Jobs that have been initiated and, as announced, will not disrupt the traffic on a major road in the city of Murcia.
The works will be done in tranches to avoid inconvenience to businesses and without encroaching on the road.
Yesterday began the proceedings with a rush of water and sanitation, while May 28 will begin the demolition of sidewalks.
To avoid problems for merchants, it is intended to emphasize the works in the peak hours of age (early morning and noon), so there will be several shifts.
Loading and unloading of material will be made on the six or seven in the morning in order not to disrupt traffic.
According to the projections will need to download a total of 68 truckloads of material.
The works are made from the Plaza to Plaza Martínez Fuensanta Tornel.
The materials to be used will be granite curbs and granite flooring in white and black in various sizes and six inches thick.
Source: Ayuntamiento de Murcia