Community Development Ministry and City Hall reached a "historic agreement" to set the stages and deadlines for the work of burial of the AVE in Murcia (30/07/2015)

The execution of works shall be four years as from the delivery of comprehensive excavation project, whose term expires at the end of 2016

The Board of Directors of Murcia High Speed ​​society composed of the Autonomous Region, the Ministry of Development and the city of Murcia to the arrival of the high speed to the city of Murcia, today reaffirmed the commitment to implement the tunneling work the arrival of the railway network in the capital of the region, for which planning has set the following phases, timelines and budget of the whole project underground railway construction in Murcia.

This was announced by Minister of Public Works and Infrastructures, Francisco Barnabas, after a meeting between state, regional and local administrations in the Ministry of Development, which was chaired by Secretary of State for Infrastructure, Transport and Housing, Julio Gómez-Pomar .

Barnabas described as "historic" agreement acquired within the Company which is to "determine the implementation of the next phases of integration, once the drafting of the comprehensive project of underground complete", which is currently under Writing under the 2006 Protocol and it should be delivered late next year.

The Minister said that "they are making great progress" in the complete integration of the arrival of the high speed rail, both for people and goods, "but said that" we must continue working to consolidate the gains achieved so far with the AVE, especially in integrated burial ".

In this sense, he noticed that "after the development of the works being carried out on the stretch of access to Murcia and its permeation, work continues in the first place, with the burial of the beach road and railway El Carmen and then with the other sections of construction in the Path of the Garres, depression Nonduermas-Barriomar and burial in Nonduermas, in care of the technical criteria and interests and social will-being of the citizens of Murcia "reported Barnabas.

The deadline for execution of the works of these phases "will be four years," computed from project delivery to Murcia Company High Speed, and shall be borne by Adif-High Speed, the Autonomous Community and the City, based percentages established in the sixth clause of the Protocol of 2006. Thus, Adif-High Speed ​​would cover 66 percent, the Community, on 26 percent and the City, 8 percent.

During the meeting, "the good progress of the proceedings on the line in the area of ​​Murcia, specifically the stretch of Murcia and permeabilization access to rail passing through the capital of the region drawn" also analyzed said Barnabas and He said that "in addition, we are working on drafting the comprehensive project to build the burial of the railway network of the city of Murcia, which was awarded last March, with a deadline of writing 18 months."

Source: CARM

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information