The Board of Urbamusa, chaired by the Mayor of Murcia, Miguel Angel House, has approved the budget for 2015 foresees revenues of 11,168,747 euros and expenses (management, operations, personnel, etc) of 11,167,222 euros , obtaining a profit of approximately 1,500 euros.
In addition, the meeting, which was attended by the Director of Development, Public Works and Planning, Francisco Barnabas, reported on the works of Phase II of coastal.
Currently he is working on seven sections of the North Coast and three of the South Coast, all sections will be open to traffic in August.
In particular, are under construction road linking La Nora with the square of the UCAM, the square of the UCAM with Guadalupe, wireless access Developments north Cabeza de Torres, northern access road Cabezo Torres with A4, link A4 road industrial area, highway that connects the industrial area with the roundabout Developments-Santomera and doubling of the A4 road access and access to the A7 motorway.
In total just over 6 miles.
All work will be completed in August excluding the section of the gazebo UCAM to Guadalupe to be completed in May.
In the South Coast is working on the road connecting El Palmar-La Alberca, viaduct over the A-30 and free El Palmar in San Ginés.
All works will be completed in August excluding the section El Palmar-San Ginés, which ends in May.
The budget of the stretches of coastal works is 23.5 million euros.
Source: Ayuntamiento de Murcia