In order to ensure the safety of pedestrians, the Department of Urban and Infrastructure Quality raises the need to begin work on the sidewalk located on the stretch of Avenida Miguel de Cervantes, between Calle Pintor Molina Sánchez and Fernando Alonso Navarro;
well as on the two streets located in bottom of bag perpendicular to the square Santona.
At present the existing sidewalk on the route indicated in the Miguel de Cervantes Avenue is very poor and even non-existent in some stretches.
The procedure is as follows: the sidewalks will be demolished and the same shall be renewed, and build a new sidewalk on the stretch of the avenue that lacks it.
A parking area will also be created.
Regarding the two perpendicular streets fund sack Santoņa Square, they have stone slab sidewalks that are in disrepair and whose renewal is needed to rush to get a safer pedestrian movement and an aesthetic appearance and
more suited to the functional urban environment.
Tasks will include the provision of a prefabricated cobblestone pavement and placing a curb to regularize the union of the sidewalk and the road.
The budget is the amount of 48,725.14 euros in Miguel de Cervantes Avenue and 58,597.61 euros in the two perpendicular streets fund sac street plaza Santoņa.
Regarding the execution time, is considered sufficient within two months for the full completion of the work from the date of lifting the certified report stakeout.
Source: Ayuntamiento de Murcia