Platform Affected by peih accuses the city of Murcia to tax by an infrastructure that does not exist (04/07/2014)

The Special Plan of Hydraulic Infrastructures Murcia (peih) was approved in December 2004 with a commitment to be reviewed by the City and EMUASA every three years.

The document has never been reviewed, nor his works and therefore costs the same

The peih contains much higher than the market, as it was based on a forecast of population growth in the northern area completely erroneous prices.

Those affected have been rotated them unfair fees infrastructures that mostly have failed to run (just has run 14.87%)

The Platform of People Affected by the Special Plan of Hydraulic Infrastructures Murcia (peih) and the excessive taxes (IBI) Murcia City Council met yesterday for the second time to mark an action plan on what they consider a "slow and mismanagement "by the Consistory in relation to the northern part of town.

During the meeting, the 450 affected the current members expressed great concern about the extra assumed to mark the peih, which adds to the already denounced payment of IBI overrated.

"We found a plan to expand the oversized and overly expensive north and a municipality seeking to recover for an infrastructure that does not exist.

In fact, given the current situation, some will not be necessary in many years, "explains José Apirm president and spokesman for the Platform of People Affected.

"Many compensation boards have failed to cope with the high payments and now the council is gathering information to go to private citizens, which of the Platform describe as intolerable."

The complaint of those affected is based which, when adopted in 2004, the Water Infrastructure Plan, the City Council promised to review it every three years to ensure its viability.

However, "the city of Murcia did not fulfill its obligation" and you have not reviewed.

Because the reality of urban growth in the north (between New Condomina and Llano de Brujas) directly affected by this Plan, has been completely different from what was planned, private landowners and developers have been forced the City to continue paying some fees to cover the oversized peih, which was run only 14.87% of the projected private investment.

The planned government investments have not been developed in the last nine years and "surprisingly, no investments allocated to the City of Murcia this Special Plan".

"It is completely irresponsible for the council not having reviewed the peih, which has led many owners, both individuals and developers, are bearing the cost of works that were not executed.

It is clear that demand an exorbitant price to pay for an infrastructure that does not exist yet and see if it exist, "says Hernandez," We have no interlocutor by the City Council and Planning has given us no alternative. "

Murcia City Council in July 2013, initially approved a document Changing the Infrastructure Plan which stipulates that those who have already passed the land subdivision, but have not yet paid the peih, "will continue to do with the prices and sizing the initial document not reviewed, which we believe is unfair because they know keep asking taxpayers to pay more than they receive, but not rectified.

We also believe that those who have already paid an extra cost should receive financial compensation. "

This document does not revise the peih not including technical data with the new values.

In 2013 a dispute was brought to the City by the peih

A set of promoters, accompanied by the Association of Real Estate in the Region of Murcia (Apirm), brought an in 2013 against the City to request the annulment of peih and therefore of the drawings made.

"There are, in our view, a number of irregularities in the Special Water Infrastructure Plan that have been referred to the courts," says Hernandez.

However, the constitution of the platform during the 2014 Affected answered that the City, through the Department of Finance has asked the Boards information about the owners that make them up.

We understand that the intent is directly claim to private owners "in an attempt to make the money that the Compensation Boards can not pay, so take the citizens directly.

Can not have that, plus they consider it an illegal, so the platform gives voice to both professionals and individuals, also will be affected by the peih "Hernandez concluded.

In numbers

The land owners, both individuals and developers, are not against paying the development costs, but are opposed to certain payments to which the City has forced them to build because, without payment peih the Consistory not sign the documentation needed to develop land subdivision projects.

"For example, a homeowner in Churra have to pay 3,000 € more to build one in your home Patiño.

And the owner who has not yet started the development process need not know how much to pay because the City Council has not been defined.

There is a total lack of transparency and agility. "

Currently, they are affected by peih about 30 partial plans of the municipality of Murcia and, according to Hernandez, "there are developers who have had to spend over a million euros".

According to the data handled by the Promoters Association, based on recent reports, the amount of the execution of the works undertaken by the Municipality of Murcia for the development of peih amounts to 32,717,980 euros and the drawings made by the City 43,608. 491 euros, so there would be a balance in favor of the City of 10,890,510 euros.

Source: Agencias

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information