Regarding the works for the construction of a paddle in Puebla de Soto, the city of Murcia notes the following:
1.
In the plenary session of the Municipal Council of Puebla de Soto held last September 23, 2013 was agreed, as stated in the relevant official record, that "there is demand by many residents of the hamlet of installing a track paddle, intends to request approval of a project for the construction of this track.
It was agreed unanimously. "
Two.
Subsequently, the Department of Decentralization, at the request of the President of the Municipal Board of Puebla de Soto, decided to take the local request.
This agreement contained in the minutes of the Plenary of the Municipal Board held on November 18, 2013.
Three.
The Municipal Board of Puebla de Soto, as reflected in the minutes did not authorize any project or budget.
April.
Decentralization Municipal technicians drafted the relevant construction project runway.
Projected costs amounted to 23,829, 79 euros.
May.
The minutes of the plenary session of November 18 has that "paddle which originally was going to make a budget of the Municipal Board, the Department who will finally be with your budget to carry out".
6.
In the same act, the headman said the investment of the Municipal Board that was to be used to track other works would take advantage of the hamlet, which is also detailed and are running.
7.
The Governing Board of the City of Murcia, in strict application of the Law on Public Sector, awarded the work for a total of 21,900 euros.
8.
At present, the track is still under construction.
Source: Ayuntamiento de Murcia