Socialist spokesman, Pedro Lopez, denounces the continuing delays in the works of this infrastructure, which date was scheduled for January 2010 and the problems that these breaches of time limits are causing traders who decided to open a business in area
In addition, Lopez reports that the parking concessionaire wants to give up managing the car park by successive delays and seeks compensation to the City of 45,294 euros and the return of the securities offered (€ 277,681)
PSOE spokesman, Pedro Lopez, laments once again the custom adopted by the City of mishandling municipal works.
So, this time and after the ordeal of the Romea Theatre, refers to the new municipal building built between Ibn cArabi streets and Marques de los Velez, the headquarters building formerly the Planning Department that has cost more than 25 million euros the public purse.
Expected completion date for such infrastructure dates back to January 2010, although they have approved three extensions of the contract.
City Council officially received the work on 21 October 2011, but so far nothing is known.
Again, Lopez complaint continued delays in a poorly planned municipal works are causing conflicts, and what is worse, out-there outrage among small business owners who decided to open their business in the area for non-compliance in terms of opening of the building.
"If small business is already bad in this county, missing badly managed that the City works with more and more delays to finish sink," said Socialist spokesman.
You want to go
The result of this poor planning, continues López-the local government also faces a problem with the parking concessionaire for the new building which has notified its intention to give up their holdings claiming a delay of more than six months in the delivery of parking and City Council seeks compensation and 45,294 euros and the return to collateral worth € 277,681.
Plus
Other data reinforce the problem of poor planning is that as the new building is still closed and it is unknown when open, the City Council approved, the Board of Governors on 29 February, the renewal of the lease of a three-storey building Montijo street to service the council of City Planning.
"It's five months' rent from the 16 January at a rate of 7708 euros a month," said Lopez.
In addition, the Board of Governors, said the spokesman of the PSOE 21 December, the Consistory also took computer equipment procurement of the new building from the street Ibn cArabi.
Computer hardware, fiber optics connected with the other municipal buildings totaling 850,000 euros and within two months.
Source: PSOE Murcia