The performance has a deadline of one month and will be undertaken in a stretch of 2.7 kilometers
The Department of Urban Quality and Infrastructure, who runs Ana Martinez Vidal, conditioned central median islands and traffic regulating new Beniaján Avenue.
The layout of the road run, corresponding to the central median, begins at the Puente de La Fica and continues to the east, intersects the future Ronda de Levante, coinciding with the trace to connect with the MU-300 (next to Main Street in Rincon Villanueva).
It adopts the following distribution of layer thicknesses and characteristics:
Print Âżnonwoven geotextile felt after heat treatment 100%.
Gray polypropylene continuous filament high tenacity.
MD tensile strength 10 kN / m.
Laminar mass 175 g/m2.
Âż5 inches from crushing limestone aggregates, size 20/40 mm.
The length of the performance in this first phase is 2763.917 meters.
The performances have a deadline of one month from the signing of the minutes of evidence and a budget setting out execution by contract, to 56716.87 euros.
This infrastructure executed chapter looked platform exclusively filmed and intersections with other roads with which he passed, but did not include the chapter on conditioning medium.
One year after its commissioning, the artery is close to achieving the expected traffic volume, presenting an optimal level from the perspective of functional circulatory system.
The aim of the Department of Urban and Infrastructure Quality wants to modernize the road and also undertake a major effort to improve the economic soil conditions for those who carry out their travel, work or place of residence, as they will be able to move without the danger of the bushes and weeds in the median.
Source: Ayuntamiento de Murcia