Urbamusa approved the second phase of the Coastal North and South (15/11/2011)

They are high capacity roads with landscaped median and bicycle

The Board of Directors has approved this morning Urbamusa the second phase of the Coastal North and South, the great road to improve accessibility in 14 villages.

The decision of the Board of Directors of the Municipal Urbanizadora must receive the approval of the Governing Board of the City to begin the tendering of the works.

The Mayor of Murcia, Miguel Angel House, said that it is "an important step in the modernization of Murcia and to provide the municipality a road network of the".

He also highlighted the importance of this infrastructure because "in a time of crisis where the state administration has failed to invest in public works, roads are in place that will generate jobs during its construction through collaboration between the City and Autonomous Community, with Urbamusa management. "

The Coastal North and South are high capacity roads landscaped median and bike lanes, which are designed to absorb 80,000 vehicles a day.

Urbamusa is responsible for carrying out the works.

The projects of these roads have the following characteristics:

-Accessibility: March/2010 fulfilling the Law, which defines the geometry of the new pedestrian fords, and the minimum pavement width.

It has also adapted the horizontal and vertical signs and the traffic lights.

-Environment: circular roundabouts in LED lighting is an increase in energy efficiency, as well as an increase in road safety.

Bike path is included in all sections.

-Road safety: bionda barrier protection for vehicles and protection for motorists in the necessary sections.

The vials have wooden fences to protect pedestrians and cyclists.

-Access: incorporate all existing roads to new paths-directly or by way of service, to leave no isolated area.

Intersections have remained raised in the General Plan to meet present and future.

-Gardening: maintenance of existing landscaping in previous sections with artificial turf.

On the sidewalks will be planted mulberry trees and native species at roundabouts.

-Coordination with other agencies: meetings were held and information coordination with Ministry of Development, Ministry of Public Works and Planning, Culture, Segura basin and Commonwealth Taibilla Channel, in addition to the usual and supply companies services (Iberdrola, EMUASA, Natural Gas, Board of Planters, Enagas, post office, etc.)..

The North Coast Cabezo Torres joins with La Nora, with a length of 12 kilometers.

The approved sections are:

-Connection between Nora and access roundabout UCAM-urbanized, with a length of 772 meters, an execution period of 14 months and a budget of 2.5 million euros.

-Restructuring of the existing road linking the roundabout to access UCAM-Villages and the North Coast in Guadeloupe, with a length of 1,042 meters, a deadline of 11 months and a budget of 2.7 million euros.

-Stretch that connects the Villages with access to the northern access to Cabeza de Torres, a length of 715 meters, an execution period of 14 months and a budget of 2.4 million euros.

-Road that connects the northern entrance to Cabeza de Torres with a link to the A4, with a length of 1,050 meters, an execution period of 14 months and a budget of 3.1 million euros.

Road link-A4 road access to industrial area, with a length of 610 meters, an execution period of 14 months and a budget of 2.7 million euros.

-Highway that connects the industrial area with the access roundabout Urbanziaciones-Santomera, with a length of 1,000 meters, an execution period of 14 months and a budget of 2.4 million euros.

-Doubling of the A4 road and access to the A7, with a length of 935 meters, an execution period of 14 months and a budget of 2.2 million euros.

The South Coast is the great road that will connect the beach in Torreagüera with a total length of 10.07 kilometers.

Projects approved in this road are:

-Vial of connection between El Palmar and La Alberca, with a length of 630 meters, an execution period of 14 months and a budget of 2.3 million euros.

-A30 viaduct over highway access and connection to El Palmar and the South Coast, with a length of 240 meters, an execution period of 14 months and a budget of 3.5 million euros.

-Vial of connection between El Palmar and San Ginés, a length of 1,400 m and a lead time of 7 months and a budget of 1.8 million euros.

The Municipal Urbanizadora is formed by the City and the region.

The President is the Mayor of Murcia, Miguel Ángel Cámara, and the Vice President is the Minister of Public Works and Planning, Antonio Sevilla.

Source: Ayuntamiento de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information