After the installation work platform tram Line 1 now starts the asphalting of the Avenida Juan de Borbon, from the roundabout of the cubes to the Avenue of the Fleet, with a length of 2.5 kilometers and more than 20,000 meters square at this stage of action.
These works, executed by the concessionaire Tram Murcia SA, is being made, first, in the inbound lanes and roundabouts to Murcia, and prioritizing the required installment for the arrival of the Tour of Spain on 2 September.
The asphalt works are carried out first in two lanes, leaving one free for movement, and then open these two lanes and paved and work in another.
This paving operation is further evidence of the great effort of the City Council to advance the work in the areas of greatest importance and mobility of traffic before the return from vacation.
Thus, during the month of August over the main entrance to campus and around the ring Espinardo University, the Plaza Circular has been released completely recovered four five lanes for traffic, has also been released for general access to facilities North Commercial Zone, among other actions