The Department of Development will end the drainage problems detected in certain sections of the Sucina Road, especially from Casa Pelada to Riquelme Station, on the Rambla Borrambla, in Gea and Truyols.
For this, the project and specifications have been approved to tender these works, whose estimated duration is six months and has a bidding budget of 151,231 euros.
So far, the torrential avenues that affect the area affect the layout of the road, causing flooding and trawling of farmland and leaving the road out of service at some points in its path.
The action proposed by Fomento consists of the execution of the transverse drainage works of the Sucina road (Antigua RM-F-19) at its intersection with the rambla called "Borrambla".
At present, the road in question has sections with lanes of 3.00-3.50 meters and areas where the shoulders have disappeared or these have dimensions between 0.50 and 1.00 meters.
Along its path, the road is crossed by several ramblas, which is why it is necessary to carry out transverse drainage works, modifying the roadway and installing a concrete tube of 1.20 meters in diameter.
Source: Ayuntamiento de Murcia