The Department of Development has paralyzed the works of the Avenida de la Constitución planned for the days 2, 3 and 4 December because the forecast of heavy rains does not guarantee the correct execution of the agglomerate work in the area, causing problems in the firm in the short and medium term.
They are postponed until December 9, 10 and 11
The milling and chipboard performances last three full days.
Since Friday, December 6, is a holiday, from the Department of Maintenance, Infrastructure, Services and Coordination it has been considered more convenient to postpone these works until the next days 9, 10 and 11 December, before trying to resume them this week when they finish the rains, since any unforeseen event could imply that Avenida de la Constitución was not open during the bridge, with the consequent damages for the merchants.
Source: Ayuntamiento de Murcia