Portal de Murcia

www.portaldemurcia.com

Murcia - SpanishMurcia - English
detail of Murcia

 

The bicycle gains ground and enters the heart of the historic center of the city (22/03/2017)

Antonio Navarro presents the Bicycle Action Plan 2017-2019, with new sections in vials located inside and outside the urban center and connections with pedanias, which provide continuity to existing bike lanes.

The proposal foresees an investment of 3.7 million euros to create a cycle network of 20,400 linear meters, of which almost 8,5 km are located in the streets of the historic center.

Among the first Phase 1 projects to be commissioned this year is the closing of a first ring that will connect Juan Carlos I to the river, passing through the Plaza Circular and Díez de Revenga

An investment of 3.7 million euros and a term of three years are the financial resources and the execution time provided by the City to create a cycle network of 20,400 linear meters in the city and 13,000 meters more connection with districts.

The project will allow safe, useful and accessible travel, allowing the bicycle to take center stage in urban mobility.

This is contemplated in the Plan of Action of the Bicycle 2017-2019 that has been presented to the members of the Municipal Observatory and this morning explained the Councilor for Environment, Urbanism and Huerta, Antonio Navarro, and which brings the necessary road infrastructure to Very heart of the city.

This plan is the concretion and definition of the project of the four major North-South and East-West axes presented a few months ago and with it is given a "decisive step in the present and future municipal management, since it contemplates concrete and programmed actions, Prioritizing the two key elements for the definitive and real implementation of the bicycle: the infrastructure network and the necessary financing, "said Navarro.

The technical approach is to provide continuity to existing bike lanes in the municipality and totaling 134 kilometers.

The objective now is to transform an interconnected mesh that gives fluidity to cycling journeys, joining the old stretches with the new ones, to "articulate an authentic vertebrate network of cycling paths that allow to circulate through the city and give connection to the districts," he added. The councilman.

"Normalizing and facilitating the use of bicycles as a normal means of transportation for journeys to workplaces, universities, schools, libraries or leisure areas is the main reason for this plan," said Navarro, who also recalled that "We need to give the bicycle a privileged place in the life of cities if we want to combat the effects of climate change, which has among its main causes the density of urban traffic."

"Therefore," said the owner of the Environment, "our model of city should give more space to pedestrian and bicycle trips, thus giving priority to sustainable mobility as a means of daily transportation."

The first results of this plan will begin to be appreciated before the end of the year, bearing in mind that this exercise has 100% of the funding needed to commission the drafting of all the projects envisaged.

The configuration of this cycle network runs through the center of the city, bordering and roads and roads connecting with districts and is structured in three areas: urban center, historic center and connections to pedanias.

Surroundings urban center

They will be unidirectional and bidirectional segregated bike lanes that will be added to the existing ones.

The sections of new construction will add 12 kilometers distributed in 37 streets, among them, from Juan Carlos I Avenue to Ronda Levante, May Day, Fame, Ronda Sur or Avenida de Los Dolores, among many others.

Old Town surroundings

Given the characteristics and typology of streets, it is anticipated to save the problem of the narrowness of the roads of this environment, making pedestrian traffic compatible with the light, without architectural barriers.

Once the rider leaves this environment, both the pacified zones (Zone 30) and the main bike lanes in the urban center can be incorporated.

Considering that the execution of streets with compatible pedestrian qualification is considered feasible, the estimated cycle length is 8,436 linear meters distributed in 27 streets: Mariano Girada, Sagasta, Jara Carrillo, San Nicolás, Riquelme, Alfonso X, Cetina, Salzillo, Plaza Fontes, Mariano Padilla and San Juan de Dios, among others.

Connections to districts

At present there are already some bike lanes that connect the town with pedanias, as is the case of those running along the North and South Coastal, Variante de Sangonera or the speck of the Segura River.

The proposal is to connect them and, in addition, to unite the city with the districts that are not, vertebrando a global network in the municipality.

To do this, two basic arcs are established:

· North arch: Avda. Kingdom of Murcia, Miguel de Induráin and Los Dolores, with a length of 14 km (currently running).

· Arco Sur: Via Verde Los Dolores-Torreagüera, with a length of 8 km (old train track) and Alquibla acequia, with almost 5 km (Carril Alquibla and Carril Gonzalez).

A plan with three phases

PHASE 1: Year 2017. Budget of 1 M €

Home projects:

New Sections

Typology

Estimated budget

Execution of bike lane from Plaza Circular to FICA and connections with Avda. Juan Carlos I, Avda. Juan de Borbón and Avda. Abenarabi

Segregated Bike Lane

-598.045,78 €

Execution of bike lane from Plaza Díez de Revenga to Av. Los Pinos

Segregated Bike Lane

€ 39,577.56

Execution of bike lane from Pasarela Manterola to Plaza Díez de Revenga and Plaza Circular

Bicycle / bike compatible bike lane

€ 81,046.85

Execution of bike lane in Rector Loustau Street, Obispo Frutos Street and Ronda de Garay

Segregated Bike Lane

€ 117,825.88

Execution of cycle lane in streets of the historic center

Bike / bike compatible bike lane

€ 184,578.85

Completion of closed parking spaces (Mobisec Grant)

PHASE 2: Year 2018. Budget of € 862,000

Completion of projects Phase 1. Start projects:

New Sections

Typology

Estimated budget

Execution of bike lane in Avda. Jorge Palacios, Paseo de Garay, Avda. Teniente Flomesta and Plaza Glorieta

Segregated Bike Lane

€ 391,468.03

Execution of bike path in Avda. Marqués de los Vélez.

Segregated Bike Lane

€ 92,370.98

Execution of bike path in Avda. Ronda Norte

Bicycle / bike compatible bike lane

€ 47,397.73

Execution of bike lane in Juan Antonio Perea Street, Floridablanca Street, Alameda de Colón and others

Segregated Bike Lane

€ 148,821.44

Execution of bike lane in Calle Princesa and Puente Nuevo

Segregated Bike Lane

€ 46,594.86

Execution of bike lane in a section of South Round

Segregated Bike Lane

€ 135,697.04

PHASE 3: Year 2019. Budget of 1.8 M €

Completion of projects Phase 2. Start projects:

New Sections

Typology

Estimated budget

Execution of bike lane in Calle Industria, Pintor Pedro Flores Street, Almela Costa Street and Av. Pio Baroja

Segregated Bike Lane

€ 325,034.32

Execution of bike lane in San Francisco Street, Arocas Street, Pintor Sobejano Street, Orchard Orchard Street, Silk Garden and Isaac Albéniz Street

Segregated Bike Lane

€ 939,860.05

Execution of bike path in Avda. De la Fama

Segregated Bike Lane

€ 562,274.06

This is the initial draft of the action plan, but its final configuration is open to receive proposals from bicycle associations, merchants, educational centers and the different municipal areas.

The plan also includes the installation of new public bicycle benches in locations where the proposed new cycle lanes network runs.

Equally they will be incorporating in pedanías, as the bike lanes are executed and connected with these.

Source: Ayuntamiento de Murcia

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
This website uses cookies to facilitate and improve navigation. If you continue browsing, we consider that you accept its use. More information